🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Infinium Solar

Infinium Solar is a 402 MW solar request in interconnection study in the ERCOT interconnection queue, in Howard County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0019
Grid region
ERCOT (Texas)
Developer
Jackalope Flats Solar, LLC
Connection point (POI)
#1058 Longshore_5 345kV
Location
Howard County, Texas
Technology
Solar: 402 MW
Total requested
402 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
16 August 2024
Proposed online date
July 2029

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem