United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTRolling Plains BESS
Rolling Plains BESS is a 120 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Haskell County, Texas.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0501
- Grid region
- ERCOT (Texas)
- Developer
- Haskell County BESS LLC
- Connection point (POI)
- 6104 SMOKY HILL 345kV
- Location
- Haskell County, Texas
- Technology
- Battery: 120 MW
- Total requested
- 120 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 16 August 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Haskell County; the queue data does not give exact sites.
Other requests in Haskell County
- Briggs StorageSolar + storage · 336 MW · agreement signed
- Briggs SolarSolar + storage · 324 MW · agreement signed
- Quantum StorageSolar + storage · 322 MW · agreement signed
- Solace StorageSolar + storage · 322 MW · agreement signed
- Quantum SolarSolar + storage · 322 MW · agreement signed
- Solace SolarSolar + storage · 322 MW · agreement signed
- Rubicon Alpha WindOnshore wind · 226 MW · agreement signed
- Inertia SolarSolar · 202 MW · agreement signed
- Millers Branch Solar ISolar · 200 MW · agreement signed
- Millers Branch Solar IISolar · 178 MW · agreement signed
- Millers Branch Solar IIISolar · 133 MW · agreement signed
- Grasshopper SolarSolar · 408 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem