Arnold Hills Storage

Arnold Hills Storage is a 123 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Henderson County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0089
Grid region
ERCOT (Texas)
Developer
Arnold Hills Storage, LLC
Connection point (POI)
#6926 Seven Points 138kV
Location
Henderson County, Texas
Technology
Battery: 123 MW
Total requested
123 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
24 March 2025
Proposed online date
February 2029

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.