Dodd Solar I

Dodd Solar I is a 202 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Henderson County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2021 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0261
Grid region
ERCOT (Texas)
Developer
Forest Grove Solar LLC
Connection point (POI)
Tap 138kV 6951 Eustace Southeast Switch – 3131 Forest Grove Switch
Location
Henderson County, Texas
Technology
Solar: 202 MW
Total requested
202 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
24 June 2021
Agreement signed
8 February 2025
Proposed online date
June 2028

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.