United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTDodd Solar I
Dodd Solar I is a 202 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Henderson County, Texas.
Queue statusConsented
- PlanningQueued Jun 2021 (completed)
- ConsentedFeb 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0261
- Grid region
- ERCOT (Texas)
- Developer
- Forest Grove Solar LLC
- Connection point (POI)
- Tap 138kV 6951 Eustace Southeast Switch – 3131 Forest Grove Switch
- Location
- Henderson County, Texas
- Technology
- Solar: 202 MW
- Total requested
- 202 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 24 June 2021
- Agreement signed
- 8 February 2025
- Proposed online date
- June 2028
Location
Marker shows the centre of Henderson County; the queue data does not give exact sites.
Other requests in Henderson County
- Anatole Renewable Energy StorageBattery storage · 208 MW · agreement signed
- McGee StorageBattery storage · 151 MW · agreement signed
- Wild Paw StorageBattery storage · 313 MW · in study
- Cricket StorageBattery storage · 232 MW · in study
- Old Fiddler Energy StorageBattery storage · 224 MW · in study
- Sloan StorageBattery storage · 201 MW · in study
- Kit Fox StorageBattery storage · 154 MW · in study
- Arnold Hills StorageBattery storage · 123 MW · in study
- Musgravite SolarSolar · 101 MW · in study
- Brittlebush BESSBattery storage · 597 MW · suspended
- Brittlebush SolarSolar · 594 MW · suspended
- Trinidad ESS AdditionBattery storage · 110 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem