BATTERY STORAGE · ERCOT

McGee Storage

McGee Storage is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Henderson County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0471
Grid region
ERCOT (Texas)
Developer
BT McGee Storage, LLC
Connection point (POI)
Bus #6843 at Rayburn Barton Chapel Substation
Location
Henderson County, Texas
Technology
Battery: 151 MW
Total requested
151 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
15 November 2022
Agreement signed
20 December 2024
Proposed online date
May 2026

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem