BATTERY STORAGE · ERCOTEast West BESS
East West BESS is a 123 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Kerr County, Texas.
Queue statusConsented
- PlanningQueued Oct 2022 (completed)
- ConsentedJul 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0202
- Grid region
- ERCOT (Texas)
- Developer
- East West Energy Storage, LLC
- Connection point (POI)
- 7750 LCRA MOUNTAIN HOME SUB
- Location
- Kerr County, Texas
- Technology
- Battery: 123 MW
- Total requested
- 123 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 6 October 2022
- Agreement signed
- 12 July 2024
- Proposed online date
- March 2027