Grandslam Solar

Grandslam Solar is a 122 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Atascosa County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2019 (completed)
  2. ConsentedJan 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0391
Grid region
ERCOT (Texas)
Developer
Grandslam Solar, L.L.C.
Connection point (POI)
5700 Miracle Lake 138kV
Location
Atascosa County, Texas
Technology
Solar: 122 MW
Total requested
122 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
29 July 2019
Agreement signed
29 January 2021
Proposed online date
November 2026

Location

Marker shows the centre of Atascosa County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Atascosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem