United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTReis Solar
Reis Solar is a 106 MW solar request in interconnection study in the ERCOT interconnection queue, in Atascosa County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0082
- Grid region
- ERCOT (Texas)
- Developer
- Greenalia Solar Power Reis LLC
- Connection point (POI)
- Tapping into 138 kV line (5689) Choke Canyon AEP to (5902) San Miguel Gen
- Location
- Atascosa County, Texas
- Technology
- Solar: 106 MW
- Total requested
- 106 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 2 June 2022
- Proposed online date
- August 2027
Location
Marker shows the centre of Atascosa County; the queue data does not give exact sites.
Other requests in Atascosa County
- Grandslam SolarSolar Β· 122 MW Β· agreement signed
- Paradiso BESSBattery storage Β· 101 MW Β· agreement signed
- Poteet BESSBattery storage Β· 10.0 MW Β· agreement signed
- Bluewind BESSBattery storage Β· 247 MW Β· in study
- Amphion Solar Phase 2Solar Β· 206 MW Β· in study
- Amphion Solar Phase 1Solar Β· 181 MW Β· in study
- Great Hambino BESSBattery storage Β· 123 MW Β· in study
- Amphion Solar Phase 3Solar Β· 115 MW Β· in study
- Kurtz Solar SLFSolar + storage Β· 102 MW Β· in study
- Strawberry Dunes Solar SLFSolar + storage Β· 101 MW Β· in study
- Pleasanton BESSOther Β· 10.0 MW Β· suspended
- Peeler SolarSolar Β· 210 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem