Poteet BESS

Poteet BESS is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Atascosa County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0715
Grid region
ERCOT (Texas)
Developer
HEN INFRASTRUCTURE, LLC 1
Connection point (POI)
TSP Station Name: POTEET SUB TSP Station Code: POTEETS Load Name: POTEE_1 Bus#: 5710 kV: 69
Location
Atascosa County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
17 October 2024
Proposed online date
January 2026

Location

Marker shows the centre of Atascosa County; the queue data does not give exact sites.