Great Hambino BESS

Great Hambino BESS is a 123 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Atascosa County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0654
Grid region
ERCOT (Texas)
Developer
Atascosa BESS, LLC
Connection point (POI)
#5700 Miracle Lake Substation 138kV
Location
Atascosa County, Texas
Technology
Battery: 123 MW
Total requested
123 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
11 September 2025
Proposed online date
February 2027

Location

Marker shows the centre of Atascosa County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Atascosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem