Bronc Rodeo Solar Project

Bronc Rodeo Solar Project is a 122 MW solar request in interconnection study in the ERCOT interconnection queue, in Falls County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0440
Grid region
ERCOT (Texas)
Developer
Energiekontor US Texas SP 16 LLC
Connection point (POI)
Tap 138 kV Line from Temple Pecan Creek (#3420) to the Cow Bayou Switch (#3385)
Location
Falls County, Texas
Technology
Solar: 122 MW
Total requested
122 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
3 May 2023
Proposed online date
March 2028

Location

Marker shows the centre of Falls County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Falls County