United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Roseland Solar

Roseland Solar is a 254 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Falls County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. ConsentedDec 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0205
Grid region
ERCOT (Texas)
Developer
Enel Green Power Roseland Solar, LLC
Connection point (POI)
tap 345kV 3390 Jewett - 3399 Ratsnake
Location
Falls County, Texas
Technology
Solar: 254 MW
Total requested
254 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
30 November 2018
Agreement signed
10 December 2020
Proposed online date
November 2025

Location

Marker shows the centre of Falls County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Falls County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem