United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Pasture Rose Wind

Pasture Rose Wind is a 199 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Falls County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0262
Grid region
ERCOT (Texas)
Developer
Pasture Rose, LLC
Connection point (POI)
TAP 345KV BUS 3721 STRINGER SW - 3711 BALE_S5
Location
Falls County, Texas
Technology
Wind: 199 MW
Total requested
199 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
24 March 2025
Proposed online date
June 2029

Location

Marker shows the centre of Falls County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Falls County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem