Iron Cowboy Solar

Iron Cowboy Solar is a 121 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0305
Grid region
ERCOT (Texas)
Developer
Vaquero II Solar, LLC
Connection point (POI)
Bus #8920 Haisley 4A 138 kV
Location
San Patricio County, Texas
Technology
Solar: 121 MW · Battery
Total requested
121 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
5 June 2025
Proposed online date
December 2028

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem