Jackalope Solar

Jackalope Solar is a 156 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2021 (completed)
  2. ConsentedSep 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0180
Grid region
ERCOT (Texas)
Developer
Peacock Energy Project, LLC
Connection point (POI)
8173 Gibbs 138kV
Location
San Patricio County, Texas
Technology
Solar: 156 MW
Total requested
156 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
9 February 2021
Agreement signed
30 September 2021
Proposed online date
November 2025

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County