WIND + STORAGE · ERCOT

Palo Verde Wind

Palo Verde Wind is a 298 MW wind + storage request in interconnection study in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0132
Grid region
ERCOT (Texas)
Developer
RWE Clean Energy Development, LLC
Connection point (POI)
Tap 345kV 8624 Grissom – 8455 Lon C Hill
Location
San Patricio County, Texas
Technology
Wind: 298 MW · Battery
Total requested
298 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
9 April 2024
Agreement signed
19 December 2025
Proposed online date
September 2027

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County