United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Long Point Solar

Long Point Solar is a 121 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2017 (completed)
  2. ConsentedOct 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0042
Grid region
ERCOT (Texas)
Developer
Long Point Solar, LLC
Connection point (POI)
138 KV (CEHE Sub) Tap Burke (42410) - Eagle Nest (42430) ckt 02
Location
Brazoria County, Texas
Technology
Solar: 121 MW · Battery
Total requested
121 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
15 March 2017
Agreement signed
24 October 2019
Proposed online date
April 2026

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem