United States › Grid › Interconnection queues › Idaho
SOLAR · WESTSolar project 790, Washington County
Solar project 790, Washington County is a 122 MW solar request in interconnection study in the West interconnection queue, in Washington County, Idaho, connecting to Idaho Power Company.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 790
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Connection point (POI)
- Brownlee - Ontario 230kV
- Location
- Washington County, Idaho
- Technology
- Solar: 122 MW
- Total requested
- 122 MW
- Service type
- NRIS and ERIS
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 15 April 2025
- Proposed online date
- December 2030
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem