United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 133
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Raleigh Solar Project Solar |
90.0 MW | Paused / redesign |
| York Run Solar Solar · York Run Solar, LLC |
90.0 MW | In study |
| Solar + storage project T2-038, Wallowa County Solar + storage |
90.0 MW | In study |
| Surplus; J717 Other |
90.0 MW | In study |
| Wishbone Storage (SLF) Battery storage |
90.0 MW | Paused / redesign |
| Solar project J1399, Ingham County Solar |
90.0 MW | Agreement signed |
| Solar project J847, Jasper County Solar |
90.0 MW | Under construction |
| Sunshine Valley Solar 1 Solar + storage |
90.0 MW | Agreement signed |
| Bear Island Solar Solar + storage |
89.0 MW | Agreement signed |
| Coal project 07-021, Morrow County Coal |
89.0 MW | Paused / redesign |
| Solar project J2227, Trempealeau County Solar |
89.0 MW | In study |
| Gas project 958348, Person County Gas · Duke Energy Progress, LLC |
89.0 MW | In study |
| Gas project 977565, Cleveland County Gas |
88.4 MW | In study |
| Solar + storage project 25-IC-1384, Tift County Solar + storage |
88.0 MW | In study |
| Demeter Solar Solar + storage · Demeter Solar, LLC |
88.0 MW | In study |
| Blossom Solar Solar |
88.0 MW | Agreement signed |
| Nuclear project AH1-702, Ogle County Nuclear · Constellation Energy Generation, LLC |
88.0 MW | In study |
| Solar + storage project J3223, Edwards County Solar + storage |
88.0 MW | In study |
| Onshore wind project 12-053, Polk County Onshore wind |
87.5 MW | Paused / redesign |
| Solar + storage project AH2-146, Adams County Solar + storage |
87.2 MW | In study |
| Gas project J3870, Vigo County Gas |
87.0 MW | In study |
| Gas project 415, Manatee County Gas · FPL |
87.0 MW | In study |
| Bandana Solar SLF Solar |
86.9 MW | Paused / redesign |
| Boswell Solar Project Solar · Minnesota Power |
86.8 MW | In study |
| Solar project AJ1-020, Caroline County Solar |
86.4 MW | In study |
| Solar project AG2-369, Greensville County Solar · Virginia Electric and Power Company |
86.0 MW | In study |
| Solar project LGE-GIS-2017-002, Lyon County Solar |
86.0 MW | Agreement signed |
| Waller Solar I Solar |
86.0 MW | Agreement signed |
| Solar + storage project C2-162, Yakima County Solar + storage · Golden Aces Energy, LLC |
86.0 MW | Paused / redesign |
| Solar project 20200824001, Bamberg County Solar |
86.0 MW | In study |
| Ratcliff Solar Solar · Greenalia Solar Power Ratcliff |
85.7 MW | In study |
| HappyDogSolar Solar + storage · Rosula Solar LLC |
85.5 MW | Agreement signed |
| Surplus; J1224/J1329 Other |
85.1 MW | In study |
| Harvey Solar I Solar |
85.0 MW | Agreement signed |
| Solar + storage project G0738, Umatilla County Solar + storage |
85.0 MW | In study |
| ACE Development Company, LLC Solar · ACE Development Company, LLC |
85.0 MW | In study |
| Solar project J3914, Jefferson Davis Parish County Solar |
85.0 MW | In study |
| Solar project J3988, Morehouse Parish County Solar |
85.0 MW | In study |
| Solar project AH2-115, Tioga County Solar |
85.0 MW | In study |
| Battery storage project GEN-2023-SR5, Dewey County Battery storage |
85.0 MW | Agreement signed |
| Solar project AH2-116, Cambria County Solar |
85.0 MW | In study |
| Solar project AH2-130 Solar |
85.0 MW | In study |
| Battery storage project AG2-339, Sussex County Battery storage · Cassius Blue Solar LLC |
85.0 MW | In study |
| Prairie Flyer Energy Storage Battery storage |
85.0 MW | Agreement signed |
| Solar + storage project AI1-112, Champaign County Solar + storage |
85.0 MW | In study |
| Battery storage project 124, Pierce County Battery storage |
85.0 MW | Paused / redesign |
| Solar + storage project J4029, Mississippi County Solar + storage |
85.0 MW | In study |
| Solar project GEN-2017-023, Choctaw County Solar |
85.0 MW | Agreement signed |
| Solar project J2874, Bay County Solar |
85.0 MW | In study |
| Battery storage project AH1-673, Cook County Battery storage · Big Shoulders Storage LLC |
85.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)