United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· PJM

Solar project AH2-130

Solar project AH2-130 is a 85.0 MW solar request in interconnection study in the PJM interconnection queue, connecting to EKPC.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-130
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Connection point (POI)
Clark Co - Spencer Road 138 kV
Location
Kentucky
Technology
Solar: 85.0 MW
Total requested
85.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
28 February 2022
Proposed online date
January 2026

Location

No county location in the queue data.

Power plants in Kentucky Β· Transmission lines in Kentucky

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem