🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

SOLAR + STORAGE · WEST

Solar + storage project C2-162, Yakima County

Solar + storage project C2-162, Yakima County is a 86.0 MW solar + storage request suspended in the West interconnection queue, in Yakima County, Washington, connecting to PacifiCorp.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C2-162
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Golden Aces Energy, LLC
Connection point (POI)
Tieton substation
Location
Yakima County, Washington
Technology
Solar: 86.0 MW · Battery
Total requested
86.0 MW
Service type
Energy only (ERIS)
Study phase
LGIA executed 8/4/2025, suspended 8/4/2025
Queue status
Suspended
Entered queue
15 May 2022
Proposed online date
November 2024

Location

Marker shows the centre of Yakima County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Yakima County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem