SOLAR + STORAGE · WEST

Solar + storage project 1008, Yakima County

Solar + storage project 1008, Yakima County is a 94.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Yakima County, Washington, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1008
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Black Rock Solar, LLC
Connection point (POI)
Union Gap - Midway line
Location
Yakima County, Washington
Technology
Solar: 94.0 MW · Battery
Total requested
94.0 MW
Service type
Network resource (NRIS)
Study phase
IA executed 6/23/21
Queue status
Active
Entered queue
8 March 2018
Proposed online date
November 2023

Location

Marker shows the centre of Yakima County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Yakima County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem