United States › Grid › Interconnection queues › Washington

SOLAR · WEST

Solar project TCS-14, Yakima County

Solar project TCS-14, Yakima County is a 5.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Yakima County, Washington, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Oct 2018 (completed)
  2. ConsentedMay 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
TCS-14
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
OneEnergy Development, LLC
Connection point (POI)
Circuit 5Y312 out of Sunnyside substation
Location
Yakima County, Washington
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 5/9/2022 (Includes TCS-15)
Queue status
Active
Entered queue
5 October 2018
Agreement signed
9 May 2022
Proposed online date
December 2027

Location

Marker shows the centre of Yakima County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Yakima County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem