SOLAR · WESTSolar project TCS-14, Yakima County
Solar project TCS-14, Yakima County is a 5.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Yakima County, Washington, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Oct 2018 (completed)
- ConsentedMay 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- TCS-14
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- OneEnergy Development, LLC
- Connection point (POI)
- Circuit 5Y312 out of Sunnyside substation
- Location
- Yakima County, Washington
- Technology
- Solar: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- SGIA executed 5/9/2022 (Includes TCS-15)
- Queue status
- Active
- Entered queue
- 5 October 2018
- Agreement signed
- 9 May 2022
- Proposed online date
- December 2027
Location
Marker shows the centre of Yakima County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Yakima County
- Solar + storage project 1008, Yakima CountySolar + storage · 94.0 MW · agreement signed
- Solar + storage project G1087, Yakima CountySolar + storage · 1,000 MW · in study
- Solar + storage project G1082, Yakima CountySolar + storage · 800 MW · in study
- Solar + storage project G1080, Yakima CountySolar + storage · 800 MW · in study
- Solar + storage project G1081, Yakima CountySolar + storage · 800 MW · in study
- Solar + storage project G1083, Yakima CountySolar + storage · 800 MW · in study
- Solar + storage project G0817, Yakima CountySolar + storage · 325 MW · in study
- Solar + storage project C1-40, Yakima CountySolar + storage · 150 MW · in study
- Solar + storage project G0596, Yakima CountySolar + storage · 112 MW · in study
- Battery storage project C2-204, Yakima CountyBattery storage · 100 MW · in study
- Solar project G1010, Yakima CountySolar · 70.0 MW · in study
- Battery storage project G1076, Yakima CountyBattery storage · 46.5 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem