United States › Grid › Interconnection queues › Michigan

OTHER · MISO

Surplus; J717

Surplus; J717 is a 90.0 MW other request in interconnection study in the MISO interconnection queue, in Isabella County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1031
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Salt River Substation 138kV
Location
Isabella County, Michigan
Technology
Solar: 90.0 MW · Other
Total requested
90.0 MW
Queue status
Active
Entered queue
19 August 2022
Proposed online date
July 2025

Location

Marker shows the centre of Isabella County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Isabella County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem