🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J2227, Trempealeau County

Solar project J2227, Trempealeau County is a 89.0 MW solar request in interconnection study in the MISO interconnection queue, in Trempealeau County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2227
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
Independence - Bridge Creek 69.0kV
Location
Trempealeau County, Wisconsin
Technology
Solar: 89.0 MW
Total requested
89.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
14 July 2025
Proposed online date
October 2024

Location

Marker shows the centre of Trempealeau County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Trempealeau County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem