United States › Grid › Interconnection queues › Georgia
SOLAR + STORAGE · SOUTHEASTSolar + storage project 25-IC-1384, Tift County
Solar + storage project 25-IC-1384, Tift County is a 88.0 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Tift County, Georgia, connecting to Southern Company.
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25-IC-1384
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Moultrie - North Tifton 115 kV Line
- Location
- Tift County, Georgia
- Technology
- Solar: 88.0 MW · Battery
- Total requested
- 88.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 17 April 2025
- Proposed online date
- February 2029
Location
Marker shows the centre of Tift County; the queue data does not give exact sites.
Other requests in Tift County
- Gas project IC-087, Tift CountyGas · 640 MW · withdrawn
- Gas project IC-086, Tift CountyGas · 640 MW · withdrawn
- Gas project IC-053, Tift CountyGas · 620 MW · withdrawn
- Gas project IC-054, Tift CountyGas · 620 MW · withdrawn
- Gas project IC-097, Tift CountyGas · 550 MW · withdrawn
- Solar project IC-457, Tift CountySolar · 165 MW · withdrawn
- Solar project IC-483, Tift CountySolar · 68.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem