United States βΊ Grid βΊ Interconnection queues βΊ Georgia
GAS Β· SOUTHEASTGas project IC-053, Tift County
Gas project IC-053, Tift County is a 620 MW gas request withdrawn in the Southeast interconnection queue, in Tift County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedOct 2001 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-053
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- N. Tifton Substation (230 kV)
- Location
- Tift County, Georgia
- Technology
- Gas: 620 MW
- Total requested
- 620 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Withdrawn
- October 2001
Location
Marker shows the centre of Tift County; the queue data does not give exact sites.
Other requests in Tift County
- Solar + storage project 25-IC-1384, Tift CountySolar + storage Β· 88.0 MW Β· in study
- Gas project IC-087, Tift CountyGas Β· 640 MW Β· withdrawn
- Gas project IC-086, Tift CountyGas Β· 640 MW Β· withdrawn
- Gas project IC-054, Tift CountyGas Β· 620 MW Β· withdrawn
- Gas project IC-097, Tift CountyGas Β· 550 MW Β· withdrawn
- Solar project IC-457, Tift CountySolar Β· 165 MW Β· withdrawn
- Solar project IC-483, Tift CountySolar Β· 68.4 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem