Battery storage project GEN-2023-SR5, Dewey County

Battery storage project GEN-2023-SR5, Dewey County is a 85.0 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Dewey County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Dec 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2023-SR5
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Tatonga 345 kV Substation
Location
Dewey County, Oklahoma
Technology
Battery: 85.0 MW
Total requested
85.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
15 December 2022
Proposed online date
June 2026

Location

Marker shows the centre of Dewey County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Dewey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem