ONSHORE WIND Β· SPP

Onshore wind project GEN-2009-063, Dewey County

Onshore wind project GEN-2009-063, Dewey County is a 301 MW onshore wind request withdrawn in the SPP interconnection queue, in Dewey County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2009-063
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Tatonga 345kV
Location
Dewey County, Oklahoma
Technology
Wind: 301 MW
Total requested
301 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
21 December 2009
Proposed online date
November 2011

Location

Marker shows the centre of Dewey County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Dewey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem