Onshore wind project GEN-2026-PR2, Dewey County

Onshore wind project GEN-2026-PR2, Dewey County is a 41.9 MW onshore wind request in interconnection study in the SPP interconnection queue, in Dewey County, Oklahoma, connecting to OG&E.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2026-PR2
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OG&E
Connection point (POI)
Tatonga 345 kV Substation
Location
Dewey County, Oklahoma
Technology
Wind: 41.9 MW
Total requested
41.9 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
1 December 2025
Proposed online date
December 2030

Location

Marker shows the centre of Dewey County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Dewey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem