United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1399, Ingham County

Solar project J1399, Ingham County is a 90.0 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Ingham County, Michigan, connecting to METC.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedAug 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1399
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Delhi - Churchill - Tompkins 138kV Line
Location
Ingham County, Michigan
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
17 August 2022
Proposed online date
March 2025

Location

Marker shows the centre of Ingham County; the queue data does not give exact sites.