SOLAR · MISOSolar project J3838, Ingham County
Solar project J3838, Ingham County is a 225 MW solar request in interconnection study in the MISO interconnection queue, in Ingham County, Michigan, connecting to METC.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3838
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- DELHI - TOMPKINS 138.0kV
- Location
- Ingham County, Michigan
- Technology
- Solar: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- November 2028
Location
Marker shows the centre of Ingham County; the queue data does not give exact sites.
Other requests in Ingham County
- Solar project J1399, Ingham CountySolar · 90.0 MW · agreement signed
- Battery storage project J2555, Ingham CountyBattery storage · 100 MW · in study
- Onshore wind project J1666, Ingham CountyOnshore wind · 300 MW · withdrawn
- Solar project J1919, Ingham CountySolar · 132 MW · withdrawn
- Solar project J1608, Ingham CountySolar · 100 MW · withdrawn
- Solar project J2807, Ingham CountySolar · 100 MW · withdrawn
- Solar project J1090, Ingham CountySolar · 90.0 MW · withdrawn
- Solar project J1117, Ingham CountySolar · 80.0 MW · withdrawn
- Other project G226.1, Ingham CountyOther · 60.0 MW · withdrawn
- Other project G227, Ingham CountyOther · 24.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem