United States › Grid › Interconnection queues › Oklahoma

SOLAR · SPP

Solar project GEN-2017-023, Choctaw County

Solar project GEN-2017-023, Choctaw County is a 85.0 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Choctaw County, Oklahoma, connecting to WFEC.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Hugo Power Plant 138 kV Sub
Location
Choctaw County, Oklahoma
Technology
Solar: 85.0 MW
Total requested
85.0 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
31 May 2017
Proposed online date
March 2026

Location

Marker shows the centre of Choctaw County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Choctaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem