Solar project GEN-2024-083, Choctaw County

Solar project GEN-2024-083, Choctaw County is a 250 MW solar request in interconnection study in the SPP interconnection queue, in Choctaw County, Oklahoma, connecting to ITCGP.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-083
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Hugo 345 kV Substation
Location
Choctaw County, Oklahoma
Technology
Solar: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 October 2024
Proposed online date
December 2029

Location

Marker shows the centre of Choctaw County; the queue data does not give exact sites.