SOLAR Β· SPP

Solar project GEN-2017-024, Choctaw County

Solar project GEN-2017-024, Choctaw County is a 50.0 MW solar request withdrawn in the SPP interconnection queue, in Choctaw County, Oklahoma, connecting to WFEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-024
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Frogville 138 kV sub
Location
Choctaw County, Oklahoma
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
31 May 2017
Proposed online date
December 2019
Withdrawn
May 2021

Location

Marker shows the centre of Choctaw County; the queue data does not give exact sites.