Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 112 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3451, Alcona County
Solar
120 MWIn study Alcona, MIMISO Apr 2024target 2027
Battery storage project J3133, Saginaw County
Battery storage
120 MWIn study Saginaw, MIMISO Sep 2022target 2026
New Road Storage
Battery storage
120 MWAgreement signed Loudoun, VAPJM Dec 2018target 2027
Solar project 25-IC-1373, Pike County
Solar
120 MWIn study Pike, GASoutheast Apr 2025target 2028
Onshore wind project J1769, Howard County
Onshore wind
120 MWIn study Howard, IAMISO Jun 2020target 2026
Onshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind
120 MWIn study Roosevelt, NMSPP Jun 2025
Tymochtee Solar
Solar
120 MWAgreement signed Wyandot, OHPJM Sep 2019target 2026
Solar + storage project GEN-2023-153, Perkins County
Solar + storage
120 MWIn study Perkins, NESPP Oct 2023target 2028
Solar project J2715, Acadia Parish County
Solar
120 MWIn study Acadia Parish, LAMISO Sep 2022target 2027
Elevate Bethlehem
Battery storage · Lighthouse Bethlehem, LLC
120 MWIn study Albany, NYNYISO Sep 2024target 2028
Pelham Solar
Solar
120 MWIn study Charlton, GASoutheast Sep 2023target 2025
Chester Solar
Solar
120 MWAgreement signed Chesterfield, VAPJM Dec 2018target 2027
Onshore wind project 104, Spokane County
Onshore wind
120 MWIn study Spokane, WAWest Mar 2020target 2023
Moxley Solar
Solar
120 MWIn study Jefferson, GASoutheast Nov 2020target 2024
Solar project GI-2014-9, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Oct 2014target 2016
Solar project J3168, White County
Solar
120 MWIn study White, INMISO Sep 2022target 2026
Buckaroo BESS
Battery storage · Weatherford BESS LLC
120 MWIn study Parker, TXERCOT May 2024target 2027
Wild Horse Desert Solar
Solar + storage · Wild Horse Desert Solar, LLC
120 MWIn study Dimmit, TXERCOT Dec 2024target 2028
Surplus; G736
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Battery storage project LGE-GIS-2021-013, Hardin County
Battery storage
120 MWAgreement signed Hardin, KYSoutheast Mar 2021target 2028
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023
Ridgeway Solar
Solar
120 MWAgreement signed Mckean, PAPJM Mar 2019target 2026
Excelsior Solar (Fka: Burford Five Points)
Solar + storage
120 MWAgreement signed Fresno, CACAISO Mar 20112016
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Solar project GI-2024-10, Adams County
Solar
120 MWIn study Adams, COWest May 2024target 2027
Solar + storage project 2021-G3, Pinal County
Solar + storage
119 MWIn study Pinal, AZWest Apr 2021target 2023
Solar project 649, Muhlenberg County
Solar
119 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Tracy Solar Energy Center
Solar · Tracy Solar Energy Center, LLC
119 MWIn study Jefferson, NYNYISO Oct 2018target 2028
Pradera Solar
Solar + storage · Pradera Solar, LLC
118 MWIn study Webb, TXERCOT Jul 2021target 2027
Solar + storage project AI1-174, Stephenson County
Solar + storage
118 MWIn study Stephenson, ILPJM Sep 2022target 2028
Solar project IC-616, Pierce County
Solar
118 MWAgreement signed Pierce, GASoutheast Mar 2017target 2020
Sycamore Creek Solar
Solar
117 MWAgreement signed Crawford, OHPJM Dec 2016target 2025
Onshore wind project GEN-2023-088, Okfuskee County
Onshore wind
117 MWIn study Okfuskee, OKSPP Oct 2023target 2028
Battery storage project AH2-132, Salem County
Battery storage
117 MWIn study Salem, NJPJM Mar 2022target 2024
Solar project J3539, Alcona County
Solar
117 MWIn study Alcona, MIMISO Mar 2024target 2027
Roxton Solar
Solar + storage · Roxton Solar, LLC
117 MWIn study Lamar, TXERCOT Nov 2024target 2028
Shorebird Solar
Solar
117 MWPaused / redesign Crawford, PAPJM Mar 2019target 2025
Pioneer Hutt Solar
Solar
116 MWPaused / redesign Midland, TXERCOT Oct 2022
Butcherbird Solar
Solar · Butcherbird Solar, LLC
116 MWIn study Bell, TXERCOT Dec 2023target 2027
Pioneer Hutt Solar (Alternative POI)
Solar · NextEra Energy Interconnection Holdings LLC
116 MWIn study Midland, TXERCOT Jun 2023target 2028
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Marcos BESS
Solar + storage · GRS BESS Texas Eight LLC
116 MWIn study Victoria, TXERCOT Feb 2024target 2027
Solar project J2350, Pulaski County
Solar
116 MWIn study Pulaski, ARMISO Sep 2022target 2025
Amphion Solar Phase 3
Solar · Amphion Solar, LLC
115 MWIn study Atascosa, TXERCOT Apr 2025target 2029
Gonzaga Hybrid
Wind + storage
115 MWAgreement signed Merced, CACAISO Apr 2020target 2026
Velado Storage SLF
Solar + storage · Velado Solar, LLC
115 MWIn study Dimmit, TXERCOT Nov 2024target 2028
Velado Solar SLF
Solar + storage · Velado Solar, LLC
115 MWIn study Dimmit, TXERCOT Nov 2024target 2028
Gas project J1833, Lafourche Parish County
Gas
115 MWAgreement signed Lafourche Parish, LAMISO Oct 2021target 2025
Gas project BHBE G25, Pennington County
Gas · Black Hills Power Inc.
115 MWIn study Pennington, SDWest Jun 2024target 2026
Page 112 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)