🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

BATTERY STORAGE · SOUTHEAST

Battery storage project LGE-GIS-2021-013, Hardin County

Battery storage project LGE-GIS-2021-013, Hardin County is a 120 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Hardin County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusConsented
  1. PlanningQueued Mar 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
LGE-GIS-2021-013
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
Hardin County 69 kV Substation
Location
Hardin County, Kentucky
Technology
Battery: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
LGIA signed
Queue status
Active
Entered queue
29 March 2021
Proposed online date
May 2028

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Hardin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem