United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMStonecrop Solar
Stonecrop Solar is a 82.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Hardin County, Kentucky, connecting to EKPC.
Queue statusConsented
- PlanningQueued Sep 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-320
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- CPV Stonecrop Solar, LLC
- Connection point (POI)
- Hodgenville-Stephensburg 69 kV
- Location
- Hardin County, Kentucky
- Technology
- Solar: 82.0 MW
- Total requested
- 82.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 30 September 2020
- Proposed online date
- December 2029
Location
Marker shows the centre of Hardin County; the queue data does not give exact sites.
Other requests in Hardin County
- Battery storage project LGE-GIS-2021-013, Hardin CountyBattery storage · 120 MW · agreement signed
- Solar + storage project LGE-GIS-2021-009, Hardin CountySolar + storage · 200 MW · suspended
- Solar project AH1-016, Hardin CountySolar · 180 MW · withdrawn
- Solar + storage project AF2-391, Hardin CountySolar + storage · 120 MW · withdrawn
- Solar project AF2-090, Hardin CountySolar · 110 MW · withdrawn
- Solar project LGE-GIS-2019-029, Hardin CountySolar · 100 MW · withdrawn
- Solar project LGE-GIS-2019-030, Hardin CountySolar · 100 MW · withdrawn
- Solar project AF2-260, Hardin CountySolar · 85.0 MW · withdrawn
- Solar + storage project AG1-491, Hardin CountySolar + storage · 70.0 MW · withdrawn
- Solar project AF2-309, Hardin CountySolar · 70.0 MW · withdrawn
- Solar project AF2-246, Hardin CountySolar · 58.0 MW · withdrawn
- Solar + storage project AG1-096, Hardin CountySolar + storage · 55.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem