United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR + STORAGE Β· PJMSolar + storage project AF2-391, Hardin County
Solar + storage project AF2-391, Hardin County is a 120 MW solar + storage request withdrawn in the PJM interconnection queue, in Hardin County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedJan 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-391
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Naturgy Candela DevCo LLC
- Connection point (POI)
- Central Hardin 69 kV
- Location
- Hardin County, Kentucky
- Technology
- Solar: 120 MW Β· Battery
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- June 2023
- Withdrawn
- January 2025
Location
Marker shows the centre of Hardin County; the queue data does not give exact sites.
Other requests in Hardin County
- Battery storage project LGE-GIS-2021-013, Hardin CountyBattery storage Β· 120 MW Β· agreement signed
- Stonecrop SolarSolar Β· 82.0 MW Β· agreement signed
- Solar + storage project LGE-GIS-2021-009, Hardin CountySolar + storage Β· 200 MW Β· suspended
- Solar project AH1-016, Hardin CountySolar Β· 180 MW Β· withdrawn
- Solar project AF2-090, Hardin CountySolar Β· 110 MW Β· withdrawn
- Solar project LGE-GIS-2019-029, Hardin CountySolar Β· 100 MW Β· withdrawn
- Solar project LGE-GIS-2019-030, Hardin CountySolar Β· 100 MW Β· withdrawn
- Solar project AF2-260, Hardin CountySolar Β· 85.0 MW Β· withdrawn
- Solar + storage project AG1-491, Hardin CountySolar + storage Β· 70.0 MW Β· withdrawn
- Solar project AF2-309, Hardin CountySolar Β· 70.0 MW Β· withdrawn
- Solar project AF2-246, Hardin CountySolar Β· 58.0 MW Β· withdrawn
- Solar + storage project AG1-096, Hardin CountySolar + storage Β· 55.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem