SOLAR Β· PJM

Solar project AF2-246, Hardin County

Solar project AF2-246, Hardin County is a 58.0 MW solar request withdrawn in the PJM interconnection queue, in Hardin County, Kentucky, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-246
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Connection point (POI)
Stephensburg 69 kV
Location
Hardin County, Kentucky
Technology
Solar: 58.0 MW
Total requested
58.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
27 March 2020
Proposed online date
December 2023
Withdrawn
April 2020

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.