🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project GI-2014-9, Pueblo County

Solar project GI-2014-9, Pueblo County is a 120 MW solar request with a signed interconnection agreement in the West interconnection queue, in Pueblo County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusConsented
  1. PlanningQueued Oct 2014 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2016 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-2014-9
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Comanche Substation
Location
Pueblo County, Colorado
Technology
Solar: 120 MW
Total requested
120 MW
Service type
NRIS and ERIS
Study phase
Feasibility/System Impact Study Complete Facility Study Complete System Impact ReStudy Complete LGIA Signed
Queue status
Active
Entered queue
13 October 2014
Proposed online date
December 2016

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Pueblo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem