ONSHORE WIND · SPPOnshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind project GEN-2025-GR2, Roosevelt County is a 120 MW onshore wind request in interconnection study in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2025-GR2
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- San Juan Mesa 230 kV Substation
- Location
- Roosevelt County, New Mexico
- Technology
- Wind: 120 MW
- Total requested
- 120 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 30 June 2025
Location
Marker shows the centre of Roosevelt County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Roosevelt County
- Solar project GEN-2019-003, Roosevelt CountySolar · 150 MW · agreement signed
- Solar project GEN-2019-021, Roosevelt CountySolar · 50.0 MW · agreement signed
- Solar + storage project GEN-2024-303, Roosevelt CountySolar + storage · 500 MW · in study
- Solar + storage project GEN-2024-304, Roosevelt CountySolar + storage · 500 MW · in study
- Onshore wind project GEN-2024-221, Roosevelt CountyOnshore wind · 400 MW · in study
- Solar project GEN-2024-159, Roosevelt CountySolar · 300 MW · in study
- Solar + storage project ERAS-2025-018, Roosevelt CountySolar + storage · 256 MW · in study
- Onshore wind project GEN-2024-043, Roosevelt CountyOnshore wind · 250 MW · in study
- Battery storage project GEN-2024-092, Roosevelt CountyBattery storage · 200 MW · in study
- Solar project IA-PNM-2023-16, Roosevelt CountySolar · 199 MW · in study
- Battery storage project IA-PNM-2024-01, Roosevelt CountyBattery storage · 100 MW · in study
- Onshore wind project GEN-2016-123, Roosevelt CountyOnshore wind · 298 MW · built