United States › Grid › Interconnection queues › New Mexico

BATTERY STORAGE · SPP

Battery storage project GEN-2024-092, Roosevelt County

Battery storage project GEN-2024-092, Roosevelt County is a 200 MW battery storage request in interconnection study in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-092
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Portales 115 kV Substation
Location
Roosevelt County, New Mexico
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 October 2024
Proposed online date
December 2029

Location

Marker shows the centre of Roosevelt County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Roosevelt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem