United States › Grid › Interconnection queues › New Mexico
SOLAR · SPPSolar project GEN-2019-021, Roosevelt County
Solar project GEN-2019-021, Roosevelt County is a 50.0 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2019-021
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Roosevelt 230kV Substation
- Location
- Roosevelt County, New Mexico
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 29 April 2019
- Proposed online date
- November 2027
Location
Marker shows the centre of Roosevelt County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Roosevelt County
- Solar project GEN-2019-003, Roosevelt CountySolar · 150 MW · agreement signed
- Solar + storage project GEN-2024-303, Roosevelt CountySolar + storage · 500 MW · in study
- Solar + storage project GEN-2024-304, Roosevelt CountySolar + storage · 500 MW · in study
- Onshore wind project GEN-2024-221, Roosevelt CountyOnshore wind · 400 MW · in study
- Solar project GEN-2024-159, Roosevelt CountySolar · 300 MW · in study
- Solar + storage project ERAS-2025-018, Roosevelt CountySolar + storage · 256 MW · in study
- Onshore wind project GEN-2024-043, Roosevelt CountyOnshore wind · 250 MW · in study
- Battery storage project GEN-2024-092, Roosevelt CountyBattery storage · 200 MW · in study
- Solar project IA-PNM-2023-16, Roosevelt CountySolar · 199 MW · in study
- Onshore wind project GEN-2025-GR2, Roosevelt CountyOnshore wind · 120 MW · in study
- Battery storage project IA-PNM-2024-01, Roosevelt CountyBattery storage · 100 MW · in study
- Onshore wind project GEN-2016-123, Roosevelt CountyOnshore wind · 298 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem