BATTERY STORAGE · NYISOElevate Bethlehem
Elevate Bethlehem is a 120 MW battery storage request in interconnection study in the NYISO interconnection queue, in Albany County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-130
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Lighthouse Bethlehem, LLC
- Connection point (POI)
- Albany Steam 115 kV Substation
- Location
- Albany County, New York
- Technology
- Battery: 120 MW
- Total requested
- 120 MW
- Queue status
- Active
- Entered queue
- 5 September 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Albany County; the queue data does not give exact sites.
Other requests in Albany County
- Bethlehem Energy CenterGas · 350 MW · built
- Bethlehem Energy CenterGas · 350 MW · built
- Bethlehem Energy Center UprateGas · 72.0 MW · built
- Bethlehem Energy Center UprateGas · 72.0 MW · built
- Albany County 2Solar · 20.0 MW · built
- Albany County 1Solar · 20.0 MW · built
- Albany County 2Solar · 20.0 MW · built
- Albany County 1Solar · 20.0 MW · built
- Albany LandfillOther · 6.4 MW · built
- Albany LandfillOther · 6.4 MW · built
- MM Albany LandfillOther · 4.0 MW · built
- New Scotland BESS (NYISO-C24-045)Battery storage · 1,350 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem