United States › Grid › Interconnection queues › New York
BATTERY STORAGE · ISO-NENew Scotland BESS (NYISO-C24-045)
New Scotland BESS (NYISO-C24-045) is a 1,350 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Albany County, New York.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2024 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1597
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NYISO New Scotland 345 kV
- Location
- Albany County, New York
- Technology
- Battery: 1,350 MW
- Total requested
- 1,350 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 12 December 2024
- Proposed online date
- September 2027
- Withdrawn
- June 2025
Location
Marker shows the centre of Albany County; the queue data does not give exact sites.
Other requests in Albany County
- Elevate BethlehemBattery storage · 120 MW · in study
- Bethlehem Energy CenterGas · 350 MW · built
- Bethlehem Energy CenterGas · 350 MW · built
- Bethlehem Energy Center UprateGas · 72.0 MW · built
- Bethlehem Energy Center UprateGas · 72.0 MW · built
- Albany County 2Solar · 20.0 MW · built
- Albany County 1Solar · 20.0 MW · built
- Albany County 2Solar · 20.0 MW · built
- Albany County 1Solar · 20.0 MW · built
- Albany LandfillOther · 6.4 MW · built
- Albany LandfillOther · 6.4 MW · built
- MM Albany LandfillOther · 4.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem