🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Excelsior Solar (Fka: Burford Five Points)

Excelsior Solar (Fka: Burford Five Points) is a 120 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedMar 2014 (current stage)
  3. Construction (not yet reached)
  4. OperatingOct 2016 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
678
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Panoche-Schindler #1 and #2 115 kV Line
Location
Fresno County, California
Technology
Solar: 60.0 MW · Battery: 60.0 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
31 March 2011
Agreement signed
12 March 2014
Proposed online date
December 2024
Came online
October 2016

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem