Sycamore Creek Solar

Sycamore Creek Solar is a 117 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Crawford County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Dec 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AC2-015
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Chatfield-Howard 138kV
Location
Crawford County, Ohio
Technology
Solar: 117 MW
Total requested
117 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
29 December 2016
Proposed online date
December 2025

Location

Marker shows the centre of Crawford County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Crawford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem