United States › Grid › Interconnection queues › Ohio
SOLAR · PJMSycamore Creek Solar
Sycamore Creek Solar is a 117 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Crawford County, Ohio, connecting to AEP.
Queue statusConsented
- PlanningQueued Dec 2016 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AC2-015
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Chatfield-Howard 138kV
- Location
- Crawford County, Ohio
- Technology
- Solar: 117 MW
- Total requested
- 117 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 29 December 2016
- Proposed online date
- December 2025
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Other requests in Crawford County
- Solar project AH2-164, Crawford CountySolar · 85.0 MW · in study
- Solar project AG2-149, Crawford CountySolar · 314 MW · withdrawn
- Onshore wind project W3-014, Crawford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project V1-010, Crawford CountyOnshore wind · 260 MW · withdrawn
- Solar project AH1-603, Crawford CountySolar · 200 MW · withdrawn
- Onshore wind project W3-085, Crawford CountyOnshore wind · 185 MW · withdrawn
- Onshore wind project V3-029, Crawford CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project V2-020, Crawford CountyOnshore wind · 150 MW · withdrawn
- Battery storage project AH1-604, Crawford CountyBattery storage · 150 MW · withdrawn
- 54 1.8 WTOnshore wind · 91.8 MW · withdrawn
- Solar project AG1-358, Crawford CountySolar · 58.0 MW · withdrawn
- Solar project AG2-564, Crawford CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem