United States › Grid › Interconnection queues › Washington

ONSHORE WIND · WEST

Onshore wind project 104, Spokane County

Onshore wind project 104, Spokane County is a 120 MW onshore wind request in interconnection study in the West interconnection queue, in Spokane County, Washington, connecting to Avista Utilities.

Queue statusIn planning
  1. PlanningQueued Mar 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
104
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Benewah Substation 230 kV
Location
Spokane County, Washington
Technology
Wind: 120 MW
Total requested
120 MW
Service type
NRIS and ERIS
Queue status
Active
Entered queue
2 March 2020
Proposed online date
December 2023

Location

Marker shows the centre of Spokane County; the queue data does not give exact sites.