United States › Grid › Interconnection queues › Washington

ONSHORE WIND · WEST

Onshore wind project CS25-15, Spokane County

Onshore wind project CS25-15, Spokane County is a 200 MW onshore wind request in interconnection study in the West interconnection queue, in Spokane County, Washington, connecting to Avista Utilities.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
CS25-15
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Benewah 230kV Station
Location
Spokane County, Washington
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
Request Status: Phase Two Study; Phase One Cluster Study: Complete; Phase One Re-Study: Complete; Phase Two Cluster Stud
Queue status
Active
Entered queue
30 April 2025
Proposed online date
December 2030

Location

Marker shows the centre of Spokane County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Spokane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem